Running the Analysis
- To run a control charts analysis,
from the menus choose:
Figure 1. Control Charts
dialog box
- Click Define.
Figure 2. X-Bar,
R, s: Cases Are Units dialog box
- Select pH level as the process measurement
variable.
- Select Time of measurement as the subgroup definition
variable.
- Click Statistics.
Figure 3. Statistics
dialog box
- Type 5.5 as the upper specification limit (USL).
- Type 4.5 as the
lower specification limit (LSL).
- Type 5.0 as the target value.
- Select CP, CpU, CpL, K, CpM, and Z-out in the Process Capability Indices
group.
- Select PP, PpU,
PpL, PpM, and Z-out in the Process Performance Indices group.
- Select Actual
% outside specification limits.
- Click Continue.
- Click Control Rules in the X-Bar, R, s: Cases Are Units dialog box.
Figure 4. Control Rules
dialog box
- Choose Select all control
rules.
- Click Continue.
-
Click OK in the X-Bar,
R, s: Cases Are Units dialog box.
Next