You can create a schedule to back up your VM data and store it on a storage
device that is configured in the IBM Storage Protect Snapshot for VMware
profile. You can run the schedule immediately or at a later time.
Before you begin
Before you back up virtual machines that are hosting Microsoft Exchange Server databases, mount the Exchange
databases.
About this task
During backup processing, Data Protection for VMware bypasses a guest Exchange Server database that
is dismounted, corrupted, or in a Suspend state in a Database Availability Group (DAG). Databases in
these states are excluded from virtual machine backups and are not available to restore.
Procedure
Create a schedule to back up VM by following these steps:
-
Start the Tivoli® Storage FlashCopy® Manager for VMware
GUI with either
of these methods:
-
In the Getting Started window, click Define a backup
task to open the Schedule a Backup wizard. Review the welcome
information and click Next to create the backup task.
-
In the Backup settings page, select Back up to IBM Storage Protect Snapshot as the Type of
backup to run.
-
In the General page, specify a name for the backup schedule you are
creating in the Backup Schedule Name field. The schedule name must not
contain any spaces. You can optionally add a description for the schedule.
-
In the Source page, select a VMware datacenter to view all
VMs available for that datacenter. You can also expand the datacenter and select a VMware datastore
to view all VMs available for that datastore. Select the VMs or VM templates to back up in the
selection table. If you do not know the location of a VM, select a datacenter to view all its
VMs.
Tip: Fine-tune the list of VMs by entering text in the Filter
field. The wildcard character (*) is not allowed.
-
In the Settings page, select the type of VMware snapshot to take when
backing up to the local IBM Storage Protect Snapshot for VMware
disk.
-
In the Destination page, select the device class on the local disk of
IBM Storage Protect Snapshot for VMware to back up to. The device class
defines the storage device and target disks that are used to create the hardware snapshot of the
logical units (LUNs) that are used for the datastores. The device classes must be defined in the
IBM Storage Protect Snapshot for VMware configuration before they are
available in the list.
-
In the Schedule page, you can select to run the backup immediately or
schedule the backup to run at a later time.
- To begin the backup at the completion of this wizard, select Execute
immediately.
- To schedule your backup to run at a later time, do the following steps:
- Select Schedule for later (repeated) execution.
- In the Date and time of the first backup field, specify when
you want to run the schedule for the first time.
- Specify the interval that you want the schedule to run in the How often to run the
backup field.
- In the Date and time of the last backup field, specify when
you want to stop the schedule from running. If you do not specify the date and time of the last
backup, the schedule creation cannot continue.
- If you want to include newly added or discovered VMs to future runs of this
schedule, select Newly added virtual machines are included in this backup
task. The table lists the datastores that contain the newly added VMs. This check box
has the following characteristics when selected:
- If you select all of the VMs on one datastore or datacenter, the schedule backs up that
datastore or datacenter. That is, all VMs on that datastore or datacenter, present and future, are
backed up.
- If you select one or more VMs on a datastore or datacenter (but not all), then the schedule
includes only the selected VMs and any future VMs that are added to the datastore or datacenter. The
remaining VMs on that datastore or datacenter that are not selected are excluded.
- If you rename a VM, and you select this option, the schedule backs up the renamed
VM.
To modify the list of datastores, go to the Source page and select VMs
from only the preferred datastores. Clear the selected VMs from the non-preferred datastores.
-
In the Summary page, review your backup settings and click
Finish to save your schedule. If you selected to run the backup now, the
backup operation begins immediately when you click Finish.
What to do next
After the backup schedule completes, you can verify that the VMs were backed up in the
Reports tab.