Upgrading IBM Master Data Management from Version 5.2 to Version 5.4
An instance administrator can upgrade IBM Master Data Management from Version 5.2 to Version 5.4.
- Who needs to complete this task?
-
Instance administrator To upgrade IBM Master Data Management, you must be an instance administrator. An instance administrator has permission to manage software in the following projects:
- The operators project for the instance
-
The operators for this instance of IBM Master Data Management are installed in the operators project. In the upgrade commands, the
${PROJECT_CPD_INST_OPERATORS}environment variable refers to the operators project. - The operands project for the instance
-
The custom resources for the control plane and IBM Master Data Management are installed in the operands project. In the upgrade commands, the
${PROJECT_CPD_INST_OPERANDS}environment variable refers to the operands project.
- When do you need to complete this task?
-
Review the following options to determine whether you need to complete this task:
- If you want to upgrade the IBM Software Hub control plane and one or more services at the same time, follow the process in Upgrading an instance of IBM Software Hub instead.
- If you didn't upgrade IBM Master Data
Management when you upgraded the IBM Software
Hub
control plane, complete this task to upgrade IBM Master Data
Management.
Repeat as needed If you are responsible for multiple instances of IBM Software Hub, you can repeat this task to upgrade more instances of IBM Master Data Management on the cluster.
Information you need to complete this task
Review the following information before you upgrade IBM Master Data Management:
- Version requirements
-
All the components that are associated with an instance of IBM Software Hub must be installed at the same release. For example, if the IBM Software Hub control plane is at Version 5.4.0, you must upgrade IBM Master Data Management to Version 5.4.0.
- Environment variables
- The commands in this task use environment variables so that you can run the commands exactly as
written.
- If you don't have the script that defines the environment variables, see Setting up installation environment variables.
- To use the environment variables from the script, you must source the environment variables
before you run the commands in this task. For example,
run:
source ./cpd_vars.sh
- Common core services
- IBM Master Data
Management requires the IBM Software
Hub
common core services.
If the common core services are not at the correct version in the operands project for the instance, the common core services are automatically upgraded when you upgrade IBM Master Data Management. The common core services upgrade increases the amount of time the upgrade takes to complete.
Before you begin
This task assumes that the following prerequisites are met:
- System requirements
- This task assumes that the cluster meets the minimum requirements for IBM Master Data
Management.
Where to find more information If this task is not complete, see System requirements. - Workstation
- This task assumes that the workstation from which you will run the upgrade is set up as a client
workstation and has the following command-line interfaces:
- IBM Software
Hub CLI:
cpd-cli - OpenShift® CLI:
oc - Helm CLI:
helm
Where to find more information If this task is not complete, see Updating client workstations. - IBM Software
Hub CLI:
- Control plane
- This task assumes that the IBM Software
Hub
control plane is upgraded.
Where to find more information If this task is not complete, see Upgrading an instance of IBM Software Hub. - Private container registry
- If your environment uses a private container registry (for example, your cluster is air-gapped),
this task assumes that the following tasks are complete:
- The IBM Master Data
Management software images are mirrored to the private container
registry.
Where to find more information If this task is not complete, see Mirroring images to a private container registry. - The
cpd-cliis configured to pull theolm-utils-v4image from the private container registry.Where to find more information If this task is not complete, see Pulling the olm-utils-v4 image from the private container registry.
- The IBM Master Data
Management software images are mirrored to the private container
registry.
- Cluster-scoped resources
- This task assumes that the cluster-scoped resources, such as custom resource definitions,
cluster roles, and cluster role bindings, were updated.
Where to find more information If this task is not complete, see Updating the cluster-scoped resources for the platform and services. - Image pull secrets
- This task assumes that the secrets that contain the image pull credentials for the instance
exist.
Where to find more information If this task is not complete, see Creating image pull secrets for an instance of IBM Software Hub.
Prerequisite services
IBM Knowledge Catalog is not a strict installation prerequisite, but if it is not installed, key IBM Master Data Management capabilities such as profiling, automapping, data quality workflows, and data governance will not work. Other features of the IBM Master Data Management service will function normally.
Procedure
Complete the following tasks to upgrade IBM Master Data Management:
Specifying installation options
If you plan to install IBM
Master Data Management, you can
specify the following installation option in a YAML file named install-options.yml in the cpd-cli work directory (For example: cpd-cli-workspace/olm-utils-workspace/work).
The parameter is optional. If you do not set the installation parameter, the default value is used.
The sample YAML content uses the default value.
Retain the --- syntax at the beginning of the entry to ensure that this entry is
treated as a separate document.
---
# ............................................................................
# IBM Master Data Management parameters
# ............................................................................
non_olm:
match360:
scaleConfig: x-small
| Parameter | Description |
|---|---|
scaleConfig |
Specify the size of the service.
|
Upgrading the service
To upgrade IBM Master Data Management:
-
Log the
cpd-cliin to the Red Hat® OpenShift Container Platform cluster:${CPDM_OC_LOGIN}Remember:CPDM_OC_LOGINis an alias for thecpd-cli manage login-to-ocpcommand. - Update the operator and custom
resource for IBM Master Data
Management.
Run the appropriate command to create the custom resource.
- Default installation (without installation options)
-
cpd-cli manage install-components \ --license_acceptance=true \ --components=match360 \ --release=${VERSION} \ --patch_id=${PATCH_ID} \ --operator_ns=${PROJECT_CPD_INST_OPERATORS} \ --instance_ns=${PROJECT_CPD_INST_OPERANDS} \ --image_pull_prefix=${IMAGE_PULL_PREFIX} \ --image_pull_secret=${IMAGE_PULL_SECRET} \ --upgrade=true - Custom installation (with installation options)
-
cpd-cli manage install-components \ --license_acceptance=true \ --components=match360 \ --release=${VERSION} \ --patch_id=${PATCH_ID} \ --operator_ns=${PROJECT_CPD_INST_OPERATORS} \ --instance_ns=${PROJECT_CPD_INST_OPERANDS} \ --image_pull_prefix=${IMAGE_PULL_PREFIX} \ --image_pull_secret=${IMAGE_PULL_SECRET} \ --param-file=/tmp/work/install-options.yml \ --upgrade=true
Validating the upgrade
install-components command
returns:[SUCCESS]... The install-components command ran successfully
If you want to confirm that the custom resource status is
Completed, you can run the cpd-cli
manage
get-cr-status command:
cpd-cli manage get-cr-status \
--cpd_instance_ns=${PROJECT_CPD_INST_OPERANDS} \
--components=match360
What to do next
Review the list of limitations and known issues and ensure that you complete any necessary steps to work around known problems. For details, see Known issues and limitations for IBM Master Data Management and Known issues and limitations for IBM Software Hub.
Optionally, customize your IBM Master Data Management deployment by changing configuration parameters in the custom resource. For more information, see Modifying the CR to customize your IBM Master Data Management installation.
After you complete the preceding steps, IBM Master Data Management is ready to use.