Failover prepares to host the selected applications by synchronizing the data between the
clusters. It creates the PVs that is needed by the applications to access data. Failover reverses
the direction of replication.
Before you begin
As a prerequisite, make sure that the corresponding applications on this cluster are scaled
to zero to prevent write conflicts.
About this task
Go through the following points before you do a planned failover of applications:
-
Important: In this document, the site where you enroll applications is called the
primary site and its partner site or cluster is called the secondary site. After you do a planned
failover, the cluster or site where the application is running is the primary site for that
application. The partner is the secondary site.
- The planned failover must be run only from the primary site of the application.
- Events for degraded NFS and failed cluster status are generated for enrollments and failover,
and they get removed automatically after some time.
Procedure
-
Go to .
- Click Actions >
Relocate.
The Relocate page is
displayed. The table lists applications local to the cluster that you have logged in.
- Select the applications you want to relocate to the partner cluster.
- Click Failover.
If one or more of the selected
applications have backup policies assigned, then an Attention window is displayed. Backup policies
continue to run for these applications on the current cluster. To avoid unnecessary backups, remove
policies from the applications on the current cluster.
- In the Attention window, click OK.
- In the Replicated applications page, check the status of the Primary
cluster.
Initially, the status of the primary cluster for the application is
Failing over. After successful completion of the failover, the primary cluster of the given
application must be changed to secondary site or partner cluster. The partner cluster must be
changed to the old primary cluster. After completion, it displays
icon next to the name of the Primary
cluster, and a Failover complete notification is displayed. The
IBM Storage Fusion HCI System prepares the cluster for deployment of the
relocated applications.
What to do next
You may observe issues post the failover. For more information about these issues, see
Regional-DR issues.After the failover is complete, deploy the
applications on the new primary site.