Installing IBM Storage Fusion HCI System in a disaster recovery setup
Use the sequence mentioned in this procedure to install IBM Storage Fusion HCI System with Metro-DR or Regional DR setup.
Before you begin
- For general Metro-DR prerequisites, see General Metro-DR prerequisites.
- For tiebreaker prerequisites, see Preparing the tiebreaker.
Procedure
-
Install site 1.
For the procedure to install, see the single rack installation procedure in Installing IBM Storage Fusion HCI System.
- Upgrade site 2. For the procedure to install, see the single rack installation procedure in Installing IBM Storage Fusion HCI System.
- For Metro-DR, set up the Tiebreaker. For the tiebreaker procedure, see Preparing the tiebreaker.
What to do next
- Metro-DR
- Set up Metro-DR, Enable applications for Metro-DR, Failover applications from site 1 to site 2, and Failback applications from the mirrored site to the original site. For the procedure, see Metro-DR for IBM Storage Fusion HCI System.
- Regional DR
- Configure Regional DR, enable applications, planned failover of applications, and unplanned failover of applications. For the procedure, see Regional Disaster Recovery - a Technical Preview feature.