End activities for a process
IBM Process Mining automatically detects the end activities. However, you can manually add new End Activities or change the automatically derived ones. It is recommended to specifying the actual end activity as it helps IBM Process Mining to recognize the running cases of the process.
You can use the following steps to manage the end activity:
-
In the left pane of the Manage page, click End activities.
-
Use the following steps to add an end activity:
a. In the End activities section, click Add end activity.
b. In the Activity Name box of the Add end activity dialog box, select the required activity from the list.
c. Set the End activity included to On or Off. Setting the toggle button to On indicates that IBM Process Mining must consider the selected activity as the end activity.
d. Click Add.
-
Use the following steps to edit an end activity:
a. In the End activities section, click the Edit buttoncorresponding to the activity you want to edit.
b. In the Edit end activity dialog box, do the required changes for the End activity included toggle button, and then click Save.
-
Use the following steps to delete an end activity:
a. In the End activities section, click the Delete buttoncorresponding to the activity you want to delete.
b. In the message box, click Delete.
Note: The End Activities section for the processes shared by other users, includes the button, Load values. You can use the Load Values button to load the default values set in
the parent process.