To install slide rails into the rack, use this procedure.
To install
the slide rails into the rack, complete the following steps:
- Insert the right slide rail A, marked right,
into the back-right rack mounting flange B locations.
The two rail pins will protrude through the bottom and middle holes B on
the EIA unit.
Figure 1. Installing the right slide rail into the
back of the rack
- Push on the end of the rail A to
compress the rail's spring-loaded mechanism, and insert the rail into
the front-right rack mounting flange B locations.
The rail will decompress and the two rail pins will protrude through
the bottom and middle holes B on the EIA unit.
Figure 2. Installing the right slide rail into the front of the rack
- Repeat these steps to install the left slide rail, marked left,
into the rack.
- From the front of the rack, place the latch strike C over
the pins. Finger-tighten the captive screw D into
the top pin in the front of the right slide rail A.
Figure 3. Installing the latch strike to the front of the
rails
- Repeat the previous step to install the latch strike on
the front of the left slide rail.
- Move to the back of the rack. Screw F to
attach the cable-management arm mounting bracket E to
the back of the left rail G. Finger-tighten
the screw.
Figure 4. Attaching the cable-management bracket
to the back-left rail
- If you do not plan to transport this system, continue
with Installing the HMC on the slide rails. If you
plan to transport this system, insert screw I to
attach the cable-management arm support bracket H to
the back-right rail A.
Finger-tighten
the screw. The cable-management arm support bracket can be used to
secure the cable-management arm during transport. If the mechanism
is engaged after the cable-management arm is installed, you will not
be able to slide the system from the rack.
Figure 5. Attaching
the cable-management support bracket to the back-right rail.