Installation coordination work sheet

Use this work sheet to coordinate installation tasks.

Each organization can use a separate installation work sheet and the work sheet should be completed by using the flow shown in Figure 1.

It is good practice to let each individual and team that participates in the installation review the coordination work sheet ahead of time and so that they are aware of their dependencies on other installers.

Management console installation steps M2M4 from Figure 1 have multiple tasks associated with each of them. You can also review the details for the tasks in Figure 1 and see where you can assign different individuals to those tasks that can be performed simultaneously.

Table 1. Example: Installation coordination work sheet
Organization:
Task Task description Prerequisite tasks Scheduled date Completed date
         
         
         
         
         
         
         

Table 2 is an example of a completed installation coordination work sheet.

Table 2. Example: Completed installation coordination work sheet
Organization:
Task Task description Prerequisite tasks Scheduled date Completed date
S1 Place model servers on the floor   18Aug2009  
M3 Cable the model servers and BPAs to the service VLAN   18Aug2009  
S2 Start the model servers   18Aug2009  
S3 Verify discovery of the system   18Aug2009  
S5 Verify system operation   18Aug2009  