Use this work sheet to coordinate installation tasks.
Each organization can use a separate installation work sheet and the work sheet should be completed by using the flow shown in Figure 1.
It is good practice to let each individual and team that participates in the installation review the coordination work sheet ahead of time and so that they are aware of their dependencies on other installers.
Management console installation steps M2 – M4 from Figure 1 have multiple tasks associated with each of them. You can also review the details for the tasks in Figure 1 and see where you can assign different individuals to those tasks that can be performed simultaneously.
| Organization: | ||||
|---|---|---|---|---|
| Task | Task description | Prerequisite tasks | Scheduled date | Completed date |
Table 2 is an example of a completed installation coordination work sheet.
| Organization: | ||||
|---|---|---|---|---|
| Task | Task description | Prerequisite tasks | Scheduled date | Completed date |
| S1 | Place model servers on the floor | 18Aug2009 | ||
| M3 | Cable the model servers and BPAs to the service VLAN | 18Aug2009 | ||
| S2 | Start the model servers | 18Aug2009 | ||
| S3 | Verify discovery of the system | 18Aug2009 | ||
| S5 | Verify system operation | 18Aug2009 | ||