Use this information to prepare for an expansion unit conversion.
To prepare for the expansion unit conversion, perform the following
tasks:
- Upgrade to i5/OS® Version
6 Release 1.
If you have not upgraded the i5/OS to
V6R1, upgrade now. For more information on upgrading your operating
system, see Upgrading i5/OS and
related software.
- From the System Planning Tool (SPT) application, print the SPT output before you begin
the expansion unit conversion.
You can ask your IBM® marketing
representative or IBM Business Partner to help you obtain this output during
the order process.
Note: The SPT output
can help determine the logical partition to which the new bus numbers should
be assigned and how to handle resource names. These
procedures assume a familiarity with the iSeries® server and a high level of experience
with logical partitions.
- If you are using a Linux® operating
system on your expansion unit, perform the following tasks. If you are not
using a Linux operating
system on an expansion unit, you can skip this step.
- Locate a Linux distribution
kernel that is compatible with an IBM eServer™ i5 model.
Note: Even though you are upgrading from an IBM System i® model,
you need to install a pSeries® Linux kernel
to ensure that compatibility with an IBM System i model.
- Obtain access to an installation kernel through either of the
following methods:
- Linux installation
CDs
- Network-based installation source
- Download the latest pSeries kernel to the partition virtual
disk. For SUSE Linux Enterprise Server 9, this
kernel is on the first installation CD in the /suse/ppc directory.
- Back up all server partitions using the GO SAVE option 21 option. See the GO SAVE option 21 topic to back up all logical partitions of
the server.
Note: Backing up the server partitions is vital for recovery in
case you experience errors during the expansion unit conversion.
- If you are migrating an expansion unit from a source
server to a target server during your server upgrade, ensure that you plan
for the following items:
- If you are upgrading to a new IBM System i model,
perform the following tasks to ensure that the SPCN download runs correctly:
- Ensure that the vital product data (VPD) has been added to the expansion
unit before the upgrade. See Programming vital product data for information on how to perform that task.
- Ensure that your HMC user ID has hmcsuperadmin authority. See Editing
HMC user information and roles for information about changing authority for an
HMC user ID.
- Remove the power from the expansion unit during the migration so that
the target server owns the SPCN ID of the expansion unit.