subscribe iconSubscribe to this information

Installing the system

You might need to install the system into the rack. Use the procedure in this section to perform this task.

To install the system into a rack, complete the following steps:

  1. Move to the back of the rack.
  2. If you are installing a drawer D into an existing shell C, remove the two filler plate screws A and the filler plate B.
    removing the filler plate
    A Filler plate screws
    B Filler plate
    C Shell
    D Drawer
    E Drawer screws
    Figure 1. Removing the filler plate.
  3. Carefully move any existing cables that are blocking the drawer location.
  4. Slide the drawer D into the shell.
  5. Install and tighten the two drawer screws E, securing the drawer to the shell.
  6. If you are installing two drawers, repeat substeps 1 through 5. If there is only one drawer installed in the shell, ensure that the filler plate B is installed in the blank slot.

Next topic: Attaching the RIO/HSL, power controller (SPCN), and power cables