Prerequisite for installing the rack-mounted server

Use the information to understand the prerequisites that are required for installing the server.

About this task

You might need to read the following documents before you begin to install the server:

Consider the following prerequisites before you install the server:

Important: If you are installing a ENZ0 PCIe4 expansion drawer below the following IBM systems, ensure that you leave at least 1 EIA unit of open space between the system and the drawer, and install a single EIA unit rack filler in that space. This allows for proper servicing of the drawer.
  1. NED24 NVMe expansion drawer
  2. 9105-22A
  3. 9105-22B
  4. 9105-41B
  5. 9105-42A
  6. 9786-22H
  7. 9786-42H
  8. 9043-MRX
This ensures that the ENZ0 PCIe4 expansion drawer's cable management arm has enough clearance for service procedures.

Procedure

  1. Ensure that you have the following items before you start your installation:
    • Phillips screwdriver
    • Flat-head screwdriver
    • Rack with four units of space
  2. Ensure that you have one of the following consoles:
    • HMC at version 10 release 1, or later.
    • Graphic monitor with keyboard and mouse.
    • Teletype (tty) monitor with keyboard.