Associating projects and tasks with work orders
All outbound project‐related transactions that are passed must be assigned to a project or task for costing. When transactions are entered against a work order, the integration framework uses the corresponding financial control record to retrieve and add the project and task number to the actuals transaction.
Before you begin
- The status of the project is APPR (approved).
- The end date of the project or task is equal to or later than the current date.
- The Is Chargeable checkbox for the task is selected, indicating that the task accepts charges.
To associate a work order with a project or task, complete the following steps in the Work Order Tracking application.
Procedure
- Create a work order, and enter the project and task numbers in the appropriate
fields. For actuals reporting, associate work orders with only the lowest‐level tasks (tasks without child tasks) within a work breakdown structure.
- Approve the work order.
- Record labor, material, and tool actuals transactions against the task.