Reporting labor time
You can report labor time either for an Incident as a whole, for activities on the Incident, or for both types of labor time.
- To report labor time for the Incident, either use Start Time and End Time on the menu bar, or enter start and end times in the Time Tracking table window of the Activities tab.
- To report labor time for an activity, select the activity, then enter start and stop times in the Time Tracking table window of the Activities tab.
Reporting labor time for the Incident
- In the Incidents application, display the record for which you want to report labor time.
- On the Activities tab, in the Time Tracking table window, click New Row. The Row Details open.
- Leave the Activity field empty.
- Click the Select Labor button to open the Select Labor dialog box. Select one or more Labor codes and click OK. Any labor record you select must have a craft associated with it.
- In the Labor field, click the Detail Menu icon to select an option and retrieve a value. Any labor record you select must have a craft associated with it. Alternately, enter a value in the Craft field. Any craft record you select must have a labor associated with it.
- Modify data for each row as needed.
- Fill in additional fields as needed. An asterisk indicates a required field.
- Click Save Incident.