Closing move line items

When a member of the move team completes the work on a work task, you close the move line item. Closing a parent move line item such as a person or room function also closes its associated child items such as an asset or equipment.

Procedure

  1. Select Space > Plan Moves.
  2. From the Move Designer tab, select the Show All MLI check box.
  3. In the All Move Line Items section, click Close-Out.
  4. Select the move line items that you want to close and click Close-Out.
  5. When you are finished, click Done.

Results

When you close a move line item, the status of the associated move request changes to Completed and the requester is notified.

What to do next

After a move task is completed, surveys are used to gauge the level of satisfaction with the move service. Survey results can be used to improve the move procedures or the quality of the move service.