Percent RFI overdue metric
Identifies projects that contain a high percentage of overdue RFIs, then drill in to that project and act on those RFIs that are identified as the most overdue.
- Name
- Percent RFI Overdue
- Category
- Operational
- Analysis objective for exception conditions
- Identifies the projects with a higher number of overdue RFIs than normal require attention.
- Description
- Helps project managers identify projects that need attention by showing which projects have the most RFIs overdue and by showing at the project level which RFIs are the most overdue.
- Source
- Customer Focus Group
- Measurement
- Total RFIs Overdue / Total RFIs
- Dependent data that is calculated
- RFI overdue = RFI Required By date < System Date
- Roles
- PR Manager
- Display chart types
- Value-based: Horizontal Grouped Bar (percent) Chart
- Thresholds
- Low Threshold: .1 (10%)
- High Threshold: Not Used
- Range 1: Good/Positive/Green
- Range 2: Poor/Negative/Red
- Range 3: Not Used
- Fact details
- Module: triMetricFactBusiness Object: triRFIFact
Metric Queries: triRFIFact – Metric – Percent RFI Overdue
- Drill paths
- Program
- Project Classification
- Project
- Project Manager
- Capture Period
- Interactive filters
- Geography
- Organization
- Static filters
- Active Project
- Active RFIs
- Time
- Months
- Data point refresh rate
- Monthly