Task table
The task table of the Gantt scheduler contains information about the tasks such as the task ID, task name, planned start date, total planned working hours, planned end date, and duration.
When you create or edit a task in the task table, some of the fields are editable and others are read-only. Some of the fields are automatically calculated.
The widths of the columns in the task table are resizable by dragging the column dividers in the column header. The columns can be reordered by dragging and dropping them to the preferred position.
You can choose which columns display in the task table by clicking the Choose columns
to display
button on the Gantt scheduler toolbar. Any changes that you make
to items such as column visibility, column order, and sort order per column are saved to browser
cookies when you save the project.
Task table and default column definitions
| Column | Required? | Editable? | Purpose |
|---|---|---|---|
| # | No | Yes |
Tracks the record numbering for imported Microsoft Project tasks. Defaults to
0 if the tasks are created in
Maximo® Real Estate and
Facilities, and a non-0 number if the
tasks were created in Microsoft Project and imported into
Maximo Real Estate and
Facilities.
For more information, see Microsoft project import and export. |
| ID | No | Yes | Defaults to an internal Maximo Real Estate and Facilities number on save. You can enter another value to override the default. |
| Task Name | Yes | Yes | Describes the purpose of the task. |
| Planned Start | Yes | Yes | Indicates the planned start date of the task. |
| Planned End | No | Yes | Indicates the planned end date of the task. If both this field and Total Planned Working Hours remain blank at task creation, the task is a Milestone task. |
| Planned Duration | N/A | No | Calculates the total calendar time in hours that are planned for the task. Automatically calculated based on Planned Start and Planned End or Total Planned Working Hours. |
| Type | Yes | No | Indicates the task type. Type is a required field at task creation. This field is not editable after the task is saved. |
| Total Planned Working Hours | No | Yes | Identifies the total planned working hours for the task. If this field is set to 0 and Planned End is blank at task creation, the task is a Milestone task. |
| Status | N/A | No | Represents the status of the task, such as Draft or Active. |
| Slack (Hours) | N/A | No |
Calculates the number of hours that a task can shift before it jeopardizes the planned project
start or end or individual task constraint.
For more information, see Gantt constraints and dependencies. |