Add lead time to a parent preventive maintenance (PM) record to allow advance time for
gathering tools and materials.
Procedure
- In the Preventive Maintenance application, select the appropriate parent PM record.
Attention: Add lead time only to parent PMs.
- On the PM tab, select the Lead
Time Active check box.
- In the Lead Time (Days) field, specify
a time value (in days).
- Select the Generate Work Orders action.
When you use the Generate Work Order action
on a PM in a hierarchy, all PMs in the hierarchy are evaluated. If
any PM meets frequency criteria because lead time was applied, it
triggers generation of work orders from the entire hierarchy.
- Click OK to generate the work orders.