Rescheduling assignments
In reviewing the weekly schedule for the organization, a maintenance planner sees that some work must be reassigned because of upcoming emergency work. The maintenance planner wants to leave a particular labor or crew resource available for the upcoming work.
Procedure
- In the Graphical Assignments application, click the Assignment View tab. In the resource table, locate the labor or crew entry to make available for emergency work.
- Drag the assignments that you want to reassign to another labor or crew resource. You can also reassign all the work assigned to a resource to a different day by selecting multiple records (Ctrl-click) and dragging them to a different day.
- Save the record.