Job plan costs

You can view the costs for a job plan when it is used at the site that you specify. Since you can specify that certain components of a job plan are available only at certain sites, you can view costs at different sites where the job plan elements can be used.

In the Job Plans application, you use the View Cost action to view job plan costs. The cost information that you can view includes the total labor hours required to complete the job plan, and the costs for labor, materials, services, and tools.

Example of job plan costs

Job plan 113355 requires that labor A is used at site 1 and labor B is used at site 2. Labor A has an hourly rate of $34.00 and works for one hour. Labor B has an hourly rate of $20.00 and works for two hours. You view costs for this job plan. In the Site field, you select site 1 and see a labor cost of $34.00. When you change to site B, you see a labor cost of $40.00.