As work progresses on an approved activity or task, you
can report the actual labor hours, materials, services, and tools
used.
Procedure
- Display the activity or task for which you want to report
actuals.
- Make one of the following selections:
| Option |
Description |
| If the record is an activity |
Click the Plans tab. |
| If the record is a task |
Click the Resources tab, then click
the Plans sub tab. |
- Enter the details for the actuals on the following subtabs:
| Option |
Description |
| Labor |
Report hours for labor, copy labor from the work plan, or
select planned labor. |
| Materials |
Select materials, select reserved items, and select spare
parts. |
| Services |
Select services or standard services. |
| Tools |
Select tools, copy tool data from the work plan, or select
tools that were issued. |
- Save the record.