Managing precedence constraints in the Graphical Scheduling application
You can manage precedence constraints in the graphical view to ensure that tasks are completed in a designated order.
About this task
Procedure
- To insert a precedence constraint, press Ctrl-click on
the work records that you want to link, then click Create
constraints for selected work
. All of the selected work records are now linked by constraints. The constraints are start-to-finish, in order. If a constraint does not violate any finish-to-start work requirements, the line connecting the records is blue. If a constraint violates finish-to-start work requirements, the line connecting the records is red.
- To modify or delete the constraint, right-click on the line for the constraint that you inserted. Select Edit Constraint or Delete Constraint.
- Click Save Schedule
.
- To save your changes to the work records in the work management
applications, click Commit Changes
from the Actions menu.