Work validations
You can validate the work that your schedules and work lists include and troubleshoot the results.
Validation | Warning/Error | Solution |
---|---|---|
A task or work order with no children has 0 duration. | W – 0 duration for planned work. | Modify the value in Duration field. |
Interruptible work has a specified shift that is not included in the schedule. | W – The interruptible shift selected is not included in this schedule. | Modify the value in the Interruptible field by using the Select Value icon. |
The Start No Earlier Than date plus the duration is greater than or equal to the schedule end date. | E – This work cannot be successfully scheduled with the current Start No Earlier Than date. | Modify the Start No Earlier Than date. |
The Finish No Later Than date minus the duration is less than or equal to the schedule start date. | E – This work cannot be successfully scheduled with the current Finish No Later Than date. | Modify the Finish No Later Than date. |
The location assignment dates do not fall within the schedule dates. | E – Location assignment exists outside of schedule dates. | In the Work Order Tracking application, open the parent work record and change the assignment. |
The location assignment is shorter than the parent work order duration. | E – Location assignment is not long enough to complete all work in this work package. | In the Work Order Tracking application, open the parent work record and change the assignment. |
Bottom level work records and operations do not have planned resources (craft, crew type, tool) | W – There are no required resources to determine schedule dates. | In the Work Order Tracking application, adjust the planned labor. |
Craft: A single work record or operation has a planned craft quantity greater than the available craft quantity on any shift | E – Work cannot be scheduled without enough resources in a single shift. | In the Work Order Tracking application, adjust the planned labor or the resources. |
Crew Types: A single work record or operation has a planned crew type quantity greater than the available crew type quantity on any shift. | E – Work cannot be scheduled without enough resources in a single shift. | In the Work Order Tracking application, adjust the planned labor or the resources. |
Rotating Tools: A single work record or operation has a planned tool quantity greater than the available tool quantity. | E – Work cannot be scheduled without enough resources. | In the Work Order Tracking application, adjust the planned labor or the resources. |
Planned labor exists on the parent work order when planned labor also exists at the task level. | W – Labor can be planned at the task or work record level, but not both. | In the Work Order Tracking application, adjust the planned labor or the resources. |
Duration is negative or over the threshold of 24*100 (quantity*duration). | E – Duration is negative or unreasonably high. | Modify the value in Duration field. |
Task is missing a parent work record. |
E – Tasks must have a parent work record. |
In the Activities and Tasks application, add a parent work record. |
Work record does not have a priority. |
W – Work records must have a priority. |
Modify the value in Priority field. |