Graphical view for schedules
When you view your schedule in the graphical view, the information is divided by work record type.
Schedule information for work and PM forecasts is shown separately:
- Work schedules are shown in the Activity and Resource tables.
- PM forecasts appear in the lower portion of the tables, in the PM section. The PMs and jobplans within the PM forecasts are segmented bars. If there is no job plan associated with a PM, the graphical view gives a default duration of one hour. The bars can be moved to new dates, but the durations of the job plans cannot be changed. When you edit a forecast or a job plan that is associated with a forecast, the edited segment becomes a striped bar.