Commissioning buildings
The as-built state of the building is defined in the model during construction. After you import the as-built model data into the BIM Projects application, you can commission the building and begin the process of maintaining it. Commissioning a building creates a bulk status update for all objects that are related to the building and have the specified starting status.
About this task
Location and asset records have more fields that are only valid for some status changes. The tabs in the Commission Building window provide the following options for the commissioned building:
- Asset tab
- Define the status of assets that are included and specify whether to remove references for active routes, safety plans, and update the status of child assets to the commissioned status.
- Location tab
- Define the status of locations that are included and specify whether to remove references for all routes, safety plans, and job plans.
Procedure
- In the BIM Projects application, open the project and select the Commission Building action.
- Specify the building that you want to commission.
- Select the types of records to update.
- On the tabs, define the options for the commissioned building.
- Click Commission.