Applying shifts to calendars

In the Calendars application, you can specify the range of dates over which you want to apply shifts. You can apply the shifts to the entire period defined for the calendar or for a shorter period.

Procedure

  1. In the Calendars application, select the calendar for which you want to apply a shift.
  2. Select the Define/Apply Shifts action.
  3. In the Define/Apply Shifts window, click Apply Shift(s).
  4. In the Apply Shifts with Range window, select one of the following ranges.
    Option Description
    Entire Calendar The start date and end dates reflect the dates specified for the calendar, but are read-only.
    Selected Dates The start date and end dates defined for the calendar are inserted. Change these dates, if necessary.
  5. Click OK.