Adding a calibration point to a work order data sheet

Calibration points are typically defined when you create a data sheet in the Data Sheet Template application. However, you can add calibration points to a data sheet on a work order if you need to check additional points for that asset.

Before you begin

You can add a calibration point only if the Technician Insert Points check box is selected on the data sheet in the Data Sheet Template application.

Procedure

  1. In the Work Order Tracking application, select the calibration work order.
  2. On the Data Sheet tab and in the Calibration Points table window, insert a row.
  3. Enter a numeric value for the calibration point.
  4. Specify either the discrete or analog asset function information.
  5. Save the calibration point.