Defining frequency for meter-based preventive maintenance records

You can define a frequency schedule for a meter-based preventive maintenance (PM) record to specify how often work orders are generated from it. For meter-based PMs, the generation criteria is based on metered asset usage since the target start date or completion date of previous work.

About this task

If the PM is associated with a master PM, updates to the master PM record overwrite changes you make to the frequency of the PM. If you want to prevent updates by the master PM, select the Override Updates from Master PM check box on the PM tab.

Procedure

  1. In the Preventive Maintenance application, select the PM that you want to define frequency for.
  2. On the Frequency tab, determine whether you want the PM to be on a fixed or floating schedule. In the Work Order Generation Information section, select the following check boxes as appropriate:
    • Use Last Work Order's Start Date to Calculate Next Due Date

      Select this check box if you want the due dates of generated work orders to be calculated from the target start date of the last work order. If you do not wish to calculate the next due date based on the target start of the last work order (for example, if you want the next work order to be generated when the last work order was completed instead), clear the check box.

    • Generate Work Order Based on Meter Readings (Do Not Estimate)

      Select this check box if you want work orders generated only when the defined meter reading has been reached. Clear this check box if you want the next work order due date to be based on the average metered usage.

    • Generate Work Order When Meter Frequency is Reached

      Select this check box if you want work orders for this PM to be automatically generated when the meter frequency has been reached and entered. This check box can only be selected if the Generate Work Order Based on Meter Readings (Do Not Estimate) check box has been selected.

  3. On the Meter Based Frequency subtab, click New Row.
  4. Determine how much metered activity should occur between PM work orders for this asset. In the Meter field, specify a value.
    You can only select continuous-type meters.
  5. Optional: Specify values in the Frequency and First Start Reading fields.
    The First Start Reading value will be the first meter reading at which the PM will generate work orders.
  6. Optional: To define multiple meter frequency criteria, repeat steps 3 through 5.
  7. Click Save PM.