Specify frequency for a time-based master preventive maintenance
(PM) record to determine how often its associated PMs generate work
orders.
About this task
For time-based PMs, the generation criteria is based on elapsed
time since the target start date or completion date of previous work.
Procedure
- In the Master PM application, display the master PM record
that you want to define frequency for.
- Click the Frequency tab.
- To specify the type of schedule that you want to use for
associated PMs, choose either of the following options:
- To create a fixed schedule PM, select the Use Last
Work Order's Start Date to Calculate Next Due Date check
box.
- To create a floating schedule PM, clear the Use
Last Work Order's Start Date to Calculate Next Due Date check
box.
- On the Time Based Frequency subtab,
determine how much time you want to elapse between generating work
orders from the associated PMs. Enter or select the appropriate information
in the Frequency and Frequency Units fields.
- In the Next Due Date (used during PM create
only) field, specify a value.
The value in
the Next Due Date field is the first date on
which the associated PMs generate work orders.
- Optional: Update time-based frequency information
about the associated PMs by selecting the Update Time Based
Information in Existing PMs check box.
When
you update associated PMs, the time-based information is copied to
the associated PM records.
- Save the record.