You can modify schedules and job plans on a master PM and
apply the changes to all the associated PMs.
About this task
In the Preventive Maintenance application, if an associated
PM has the Override Updates from Master PM check
box selected, the master PM does not affect its schedule.
Procedure
- In the Master PM application, display the master PM whose
associated PMs you want to update.
- On the Frequency tab, change the
master scheduling information about the PM.
- Review the information in the Work Order Generation Information
area.
The fields correspond to information that the master
PM updates on the associated PMs.
- Optional: Select the Update Existing
PMs check box to update the Extended Date field
of the associated PMs.
- On the Time Based Frequency and Meter
Based Frequency subtabs of the Frequency tab,
ensure that the following check boxes are selected to update the appropriate
frequency information:
- For time-based master PMs, ensure that the Update
Time Based Information in Existing PMs check box is selected.
The Frequency, Frequency Units,
and Alert Lead (Days) fields on the associated
PMs are updated when you update associated PMs.
- For meter-based master PMs, ensure that the Update
Meter Based Information in Existing PMs check box is selected.
The Frequency, Alert Lead,
and Generate WO Ahead By fields are updated
on the associated PMs when you update associated PMs.
- On the Seasonal Dates tab, change
the active days, dates, or both. To update seasonal dates on the associated
PMs, select the Update Existing PMs Seasonal Dates check
box.
- On the Job Plan Sequence tab, change
the job plan information. To update job plan sequences on the associated
PMs, select the Update Job Plan Sequence in Existing PMs check
box.
- Save the master PM.
- Select the Update Associated PMs action.
- Select the check box for each site that you want to update
associated PMs.
- Click OK.