Complete program
The location of the complete house building with earliness and tardiness costs program and the results are provided.
You can view the complete house building program in the
file <Install_dir>/cpoptimizer/examples/src/cpp/sched_time.cpp.
Results
Cost Value: 5000
masonry [1: 20 -- 35 --> 55]
carpentry [1: 75 -- 15 --> 90]
plumbing [1: 55 -- 40 --> 95]
ceiling [1: 75 -- 15 --> 90]
roofing [1: 90 -- 5 --> 95]
painting [1: 90 -- 10 --> 100]
windows [1: 95 -- 5 --> 100]
facade [1: 95 -- 10 --> 105]
garden [1: 95 -- 5 --> 100]
moving [1: 105 -- 5 --> 110]