An IBM® System Services Representative (SSR) uses this procedure to remove shipping brackets from the racked system.

Procedure

For each control enclosure in the rack:

  1. Remove the 3 screws shown as A in Figure 1 on each side of the shipping bracket
  2. Remove the 6 screws shown as B in Figure 1 holding the middle of the shipping bracket to the back of the control enclosure.
    Figure 1. Removing the shipping bracket from the back of a control enclosure.
  3. Pull the shipping bracket out of the rack.
  4. Remove the screws holding the rail end brackets to the shipping bracket as shown in Figure 2
    Figure 2. Removing the rail end brackets from the shipping bracket.
  5. Fit the rail end brackets to the back of the control enclosure rails as shown in Figure 3
    Figure 3. Installing the rail end brackets.