Installing a control enclosure
Following your enclosure location plan, install the control enclosure.
About this task
The installation procedure applies equally to control enclosures and
expansion enclosures.
- Lifting a control enclosure requires at least three people.
- Lifting a 2U expansion enclosure requires at least two people. Lifting a 5U expansion enclosure requires at least three people or a lifting device.
- Each control enclosure must be installed only on the control enclosure rails provided with the enclosure.
- Each expansion enclosure must be installed only on the expansion enclosure rails provided with the enclosure.
CAUTION:
- To lift a control enclosure requires at least three people.
- Install a control enclosure only onto the control enclosure rails supplied with the enclosure.
- Load the rack from the bottom up to ensure rack stability. Empty the rack from the top down.
Procedure
To install a control enclosure, complete the following steps.
What to do next
If you removed components from the enclosure to lift it, reinstall the components into the slots of the enclosure from which they were removed.