You can establish a test schedule by associating a test plan with iterations from a
project area or team area timeline. You can also list key project dates, such as the date of the
final release, code freeze, UI freeze, beta entry, or beta exit.
Before you begin
Test plan schedules are defined as iterations and timelines in the Jazz process, and as a result, test plan authors must have permission to
create and modify iterations. This permission is applied at the Project Configuration level. You can
find this permission in the Process section of Permitted Actions. The specific permission that is
required is named Modify the iteration structure
. Optionally, you can create a test plan
author role and assign this permission to that role. Otherwise, all of the Process permissions are
enabled for the Test Team Member role by default.
About this task
If a team area is associated with a particular timeline, you can select the team area in
the test plan and associate the test plan schedule with the iterations in that timeline. For more
information, see Timelines and Iterations in Rational Quality
Manager.
Note: If you want to create and use multiple timelines or associate a timeline
with a team area, in the Project Properties, you must enable team areas and support for multiple
timelines.
Procedure
-
Open a test plan.
If team areas are enabled and a team area is associated with a timeline, you can associate
the test plan with a team area by selecting a team area from the list.
-
Open the Test Schedules section of the test plan.
-
Click Browse.
-
In the Browse window, select an iteration and click OK.
The test schedule is populated with the selected iteration and its child iterations as
shown in the following image:
Tip: To get multiple iterations in the test schedule, you must define a
hierarchy of iterations. In the previous example, the iteration (4.0) represents a release and the
child iterations (M1, M2, and so on) represent iterations or milestones within the release.
-
When the iterations are displayed in the test schedule, select an iteration, and in the Actions
column, click the Edit () icon.
The Edit Properties window opens as shown in the following image:
Note: The planned start and end dates are inherited from the dates in the timeline, as are the
actual dates that are shown in brackets next to the iteration name. Initially, the planned dates and
actual dates are identical. To update the actual dates, use the timeline editor. When you make
updates in the timeline editor, the new dates are reflected in the iteration name. The planned dates
do not change. If you need to change the planned dates, make that change in the test schedule, not
the timeline editor.
-
Provide the detailed iteration properties.
-
In the Description field, type a description for the iteration.
-
In the Points field, type a points value, which is an estimate of the
execution effort for the iteration.
Alternatively, you can provide more detailed information about the distribution of these
points over time in the Plan Details window. See step 7.
-
In the Planned Defects field, type the number of projected
defects.
-
In the Defect Validity Rate field, type the number of defects that are
determined valid.
-
If necessary, click the planned start date and use the calendar to select the date.
Note: If you did not initially supply a planned end date, supply one now.
-
Click OK to save the iteration properties.
-
Repeat for each iteration in the schedule.
-
Click Save to save the schedule.
-
Optional: You can click the Plan Details () icon to estimate
the work to be done and distribute points over the iteration. The plan details are reflected in the
Planned Attempted and Planned Complete points on the Execution Trend report. Point estimates that
you enter in this window will override the points value that you previously provided for the
iteration.
- To automatically distribute points over an iteration, click the Auto Generation
icon.
- To manually distribute points over an iteration, Click the Add Row
() icon,
and type the estimated values for the date, the points to be attempted by that date, and the points
to be completed by that date. Add new rows for each date, and then click
OK.
To learn more on test plan iteration, see this video.
-
List key project dates:
-
Click the Add Key Dates icon () to add a date
that you want to track in the test plan.
-
Repeat the previous step for each date to include.
-
Click Save to save the schedule.
-
Update the dates as needed as the project evolves.