The plan dashboard shows the status and progress of plans
and provide plan statistics, such as burndown reports or other reports
that show progress over time.
About this task
To associate a dashboard to a plan:
Procedure
- Click the Dashboard tab in the plan
editor.
- Click Save. After you initially
save the dashboard, it is populated with a set of widgets.
Exception: The default dashboard is
empty for cross-project plans and any plan type that is deprecated.
Depending on the plan type, a dashboard might contain these widgets:
- Team Members
- Displays a list of contributors and roles that belong to a team
or a project area. By default, this widget is displayed in the product
backlog, or release plan, and the iteration plan, or phase plan.
- Cumulative Value Flow
- Displays an area plot of open work items, in-progress work items,
and closed work items over time. By default, this widget is displayed
in the product backlog (release plan) and the iteration plan (phase
plan).
- Plans
- Displays the total estimated time that is specified for all of
the closed work items. This widget also divides the total estimated
time by the total actual time that is spent on all of the closed work
items. By default, this widget is displayed in the product backlog
(release plan).
- Estimated Vs Actual Work
- Displays the overall progress for development plans for one or
more teams in a specified iteration. By default, this widget is displayed
in the iteration plan (phase plan).
- Optional: Customize the plan dashboard by adding
more widgets. For more information about adding, configuring, and
deleting widgets, see Adding and configuring widgets.
Tip: You
can copy and paste widgets across plan dashboards, and between plan
dashboards and regular dashboards.