Reconciling test plans with requirements in the Requirements Management application
After you have associated requirement collections with
test plans, the requirements in the Requirements Management application
might have changed. Requirements might have been added, deleted, or
modified. You can reconcile test plan coverage with the requirements
in the Requirements Management application.
About this task
Limitation: In a project that does not have
configuration management enabled, you can use the requirement reconcile
operation to find which requirements have changed. In a configuration-enabled
project, you can use the link validity status to determine which requirements
have changed.
If configuration management is enabled for your project, the following limitations apply to reconcile operations:
- The reconcile operation does not check for changed requirements. Instead, the Requirement Links section shows the updated validity status for each requirement associated with a test case. For more information about link validity, see Using link validity in CLM applications.
- Removed, deleted, and unplanned requirements are shown automatically; however, you are not required to complete an action in the Reconcile wizard. Instead, affected requirements are listed and you can open the corresponding test cases to take action.
- You cannot mark a test case as suspect during the reconcile operation.
Procedure
What to do next