Checking cables on all racks

About this task

Confirm proper cable connector seating. Use the "push, pull, push" process described here to check each connector.

Procedure

  1. At the rear of Rack-1, do the following steps at the rear of both CEC enclosures:
    1. Ensure that the following private network Ethernet cables are connected:
      Model A0x
      • Black Ethernet cables are connected to P1-C1-T1 (top) and P1-C11-T1 (top).
      • Gray Ethernet cables are connected to P1-C1-T2 (bottom) and P1-C11-T2 (second from top).
      Figure 1. CEC enclosure location codes (rear view) (Model A01)
      Figure 2. CEC enclosure location codes (rear view) (Model A05)
    2. Check each PCIe connector to ensure that it is latched.
      • Model A01:
        • P1-C6-T1
        • P1-C8-T1
        • P1-C9-T1
        • P1-C12-T1
        Model A05:
        • P1-C2-T1
        • P1-C3-T1
        • P1-C3-T2
        • P1-C4-T1
        • P1-C6-T1
        • P1-C8-T1
        • P1-C9-T1
        • P1-C12-T1
  2. At the rear of each I/O enclosure for Rack-1 and Rack-2 (if present), check each PCIe connector to ensure that it is latched. See Figure 3.
    Note: For zHyperLink or optical PCIe, pull and push the transceiver, not the optical cable.
    • P1-C7-T1
    • P1-C7-T2
    1. If Rack-2 has a coil of PCIe cables behind the I/O enclosures, loosen the cable tie at the top of the coil and move it temporarily out of the way.
    2. If DS8000 feature 1341 (20 meter PCIe3 cableset) is included with Rack-2, optical PCIe connections are used, and the Rack-2 I/O enclosure PCIe connections are made in a later step.
    Figure 3. I/O enclosure locations (rear)
  3. At the rear of each I/O enclosure for Rack-1 and Rack-2 (if present), check each bay-to-bay I2C cable connector to ensure that it is latched. See Figure 3.
    • P1-C7-T3
  4. At the rear of each I/O enclosure for Rack-1 and Rack-2 (if present), check each zHyperLink PCIe optical transceiver and cable (if present) to ensure that it is latched. See Figure 4.
    • P1-C7-C1-T1
    • P1-C7-C2-T1
    Figure 4. zHyperLink card and transceiver location codes
  5. At the rear of each I/O enclosure for Rack-1 and Rack-2 (if present), check each storage enclosure PCIe connector to ensure that it is latched. See Figure 3 and Figure 5.
    • P1-C1-T1, T2, T3, T4
    • P1-C2-T1, T2, T3, T4
    Figure 5. Device adapter card port location codes
  6. At the rear of each NVMe flash enclosure for Rack-1 and Rack-2 (if present), check each PCIe connector to ensure that it is latched. See Figure 6.
    • P1-C1-T1, T2
    • P2-C1-T1, T2
    Figure 6. Storage enclosure locations (rear view) (NVMe flash enclosure)
  7. At the rear of each rack, ensure that all power cords that are connected to each power distribution unit (PDU) connector J1 through J12 are fully seated. See Figure 7 and Figure 8.
    Figure 7. iPDU pair, locations in vertical orientation (rear)
    iPDU pair, locations in vertical orientation (rear)
    Figure 8. iPDU locations
    iPDU locations
  8. Does the storage facility that you are installing have an expansion rack?