A test is usually run in the order it was recorded. However, you might want to add some
conditions to the test that the users would actually face when interacting with the application
under test. For example, if you select a product, you want to know its manufacturing date. If the
date is not available, you want to exit. You can now add such control to the test.
-
In the Test Navigator view, browse to the test and double-click it.
-
Select the request or page that uses the IF condition and click .
-
In the Test Flow Control Details section, specify one of the following
actions:
| Action |
Description |
| Continue |
Continue running the test. |
| Exit Transaction |
Exit the transaction and continue running the test. If there are multiple levels of
transactions, specify whether you want to exit the innermost or outermost transaction. |
| Exit Loop |
Exit the loop and continue running the test. If there are multiple levels of loops, specify
whether you want to exit the innermost or outermost loop. |
| Continue to next iteration of loop |
Continue to run the next iteration of the loop after the existing iteration
completes. |
| Exit test |
Exit the test. |
| Exit user |
Exit the currently running virtual user and start running with the next user. |
| Terminate Run |
Stop the schedule, in this context, is used to