Import to the Test Environment

You import entries from the deployment archive into the target environment. To import the entries, create an import deployment specification.

When you import, you select from entries that were exported. You can either accept the default options set during the export, or change them. You can only select options that were included in the deployment archive during the export.

If you do a partial deployment of specific public folders and directory content, the import wizard shows whether packages and folders already exist in the target environment and the date and time they were last modified. You can use this information to help you decide how to resolve conflicts. When you redeploy, the wizard also shows whether the packages and folders were in the original deployment.

Procedure

  1. In the target environment, in IBM Cognos Administration, on the Configuration tab, click Content Administration.
  2. On the toolbar, click the new import button.

    The New Import wizard appears.

  3. In the Deployment archive box, click the deployment archive that you want to import.
  4. If the deployment archive is encrypted, type the password, and then click OK.
  5. Click Next.
  6. Type a unique name and an optional description and screen tip for the deployment specification, select the folder where you want to save it, and then click Next.
  7. Select the content that you want to include in the import.
    Tip: To ensure that the required target package or folder exists in the target content store, click the edit button next to the package, and check the location. If you want, you can change the target location now.
  8. Select the options you want, along with your conflict resolution choice for the options that you select.
  9. In the Specify the general options page, select whether to include access permissions and who should own the entries after they are imported in the target environment.
  10. Specify the Recording Level for the deployment history.
  11. Click Next.

    The summary information appears.

  12. Review the summary information, and click Next.
  13. Determine how you want to run the import by selecting the action you want.
  14. In the Actions column, click the run with options button.
  15. Click Now to run the import immediately, or click Later, and enter the time that you want the import to run.
  16. If you want to upgrade the report specifications, click Upgrade all report specifications to the latest version.

    You can also use the Schedule Management tool to schedule a task to run on a recurring basis, and view a list of scheduled tasks.

Results

You can now test the deployment.