End of Day SLC calendar schedule
Because the bank wants to monitor the start of the EndOfDay Process, they created an SLC calendar schedule.
The specified the following information in the calendar schedule. (This schedule was later selected when the “End of Day” SLC was defined.)
Field | Value |
---|---|
Name | End of Day |
Description | Monitor for start failure of EndOfDay process |
Schedule Type | Calendar Schedule |
Parameters | |
Calendar Name | Daily |
Time Zone | (UTC 5:00) Central Time (US & Canada) |
Normal Start Range (NSR) | |
Start Time | 17:55 |
End Time | 18:00 |
Permissions (Roles that can edit this action) | Operations Admin CD3 |