If you are a system administrator, you can synchronize a schedule's data in Content
Manager with the data stored in the notification database.
About this task
Occasionally, high volumes of event activity may cause schedule data in the notification database
to diverge from the values in the Content Manager database. For example, you may set a schedule to
run every day at 8 a.m. However, it runs at irregular times, instead of at the scheduled time. To
resolve this issue, you can synchronize selected schedules or all schedules.
Note: You can synchronize schedules only by clicking
. This
option is not available if you click
My schedules and subscriptions in the
Personal menu

.
Procedure
- Click the Open menu icon
, and then select
.
- If you want to synchronize all the schedules that match certain criteria, follow these
steps:
- Click the Synchronize schedule icon
in the upper right
corner of the Activities page.
Tip: If the Synchronize schedule icon

does not appear and you
have enabled schedule synchronization, refresh your browser.
The Schedule synchronization window appears:
- Select a parameter and specify its values.
- Task ID
- Enter one or more
TaskID
values from the notification database that correspond
to schedules.
- Creation time
- Define a time period in which the schedules were created by specifying a start time, an end
time, or both. If no start time or end time is entered, all schedules are synchronized.
- Modification time
- Define a time period in which the schedules were last modified by specifying a start time, an
end time, or both. If no start time or end time is entered, all schedules are synchronized.
- Click Apply.
The schedules that you specified are synchronized.
- If you want to synchronize selected schedules, follow these steps:
- Select Schedule in the view selector box.
- Select the check boxes for each schedule that you want to synchronize.
- Click Synchronize schedule in the blue table
header.