After the operator upgrades your document processing components, you need to do extra
configuration to complete the upgrade process.
Procedure
To complete the upgrade for Document Processing
- Upgrade your applications that are based on previous versions of the Batch Document
Processing Template and Document Processing Template. For more information, see Upgrading document processing applications.
- Update your existing projects.
If you want to work with a document processing
project that you created in the previous version, you must open the project in the updated document
processing designer, retrain your classification model, reanalyze all training files individually
and verify the annotations, and make the training files ready for training before you retrain the
extraction model. After these steps, you can create a new version of the project.
- Redeploy projects that were deployed before the upgrade.
For Project
Admins-
<projectName> to be able to deploy projects, a member of the Doc
Processing Manager or Doc Processing Analyst team must first redeploy that project.
The Doc
Processing Project Admins team must be added as a team member of the BTS Creators team to give the
Project Admins-<project> team the ability to deploy.
- Optional: If the
shared_configuration.sc_egress_configuration.sc_restricted_internet_access
parameter value is already set to
false
in your custom resource and if you
want to enable restricted internet access after you complete the upgrade to 24.0.0, then you can set
the shared_configuration.sc_egress_configuration.sc_restricted_internet_access
parameter value to true
. If you set the value to
true
, then you need to create a custom network policy. For more information,