Commit IBM Storage Scale version update
This operation commits the IBM Storage Scale version that was updated for a deployed IBM Storage Scale instance.
About this task
This operation can be performed only on the IBM Storage Scale Primary server instance and on the IBM Storage Scale Client instance. If you attempt to run this operation on the Mirror or Tiebreaker instances, you receive an error.
This operation will not
complete successfully in the following cases:
- The updated IBM Storage Scale Server deployment is in update pending state, meaning that the update is not yet committed on all the IBM Storage Scale server instances in the cluster. Ensure that the IBM Storage Scale instance update process has completed successfully, and that you used the Commit function in the instance details to commit the update for all IBM Storage Scale Server instances in the cluster.
- When updating the IBM Storage Scale Client, the IBM Storage Scale Server that the client communicates with is not yet upgraded and committed to the new IBM Storage Scale version. The commit operation verifies that the IBM Storage Scale Servers are already updated and committed before committing the client.
Procedure
- Expand the Update GPFS operations section of the GPFS_Manager operations.
- Expand the Commit GPFS version update node.
- Click Submit.
- Click Confirm when asked to validate your request.
Results
When you run this operation, a new entry is displayed under
the Operation Execution Results list, with
the name Commit GPFS version update. When completed,
the status of the operation changes from Active to Done,
and the Return Value column displays a message
that the operation has been performed, and a link to the resulting
log file, similar to the following example:
GPFS-Manager.11403015464726.GPFS_Manager: Click here to open the status.
Click the link to display the log results. Verify that there are no errors in this log.