Use sequence flows to connect activities and other modeling
constructs to establish the process flow.
Before you begin
To perform this task, you must be in the IBM® Process
Designer desktop
editor.
Procedure
- Open the Process Designer desktop editor.
- Open a process application that contains a business process definition (BPD) in the Designer
view.
- From the palette, click to select the Sequence Flow tool.

- In your process diagram, click the first modeling construct
(normally the start event), and then click the construct that follows
the start event in the process flow. The Sequence Flow tool connects
the two items.
- Continue creating sequence flows as needed. If more than
one sequence flow leaves the same modeling construct, the first one
you add is the default sequence flow. Subsequent sequence flows that
originate from the same construct are only followed under certain
conditions. To specify the conditions under which a non-default path
is followed:
- Select the sequence flow in the diagram.
- In the Behavior section of the
Properties view, specify the condition under which the process execution
follows this sequence flow. The default sequence flow is
followed whenever the conditions specified for the non-default flows
are not met. Conditions for all outgoing sequence flows other than
the default sequence flow are required or mandatory.
- When you are finished establishing the process flow, click
the Selection Tool in the palette or press Esc to