Escalations
You can use IBM® Integration Designer to model escalations for tasks that are in the activation states of ready, running, claimed, or subtask.
You can define escalations for any task during modeling or, dynamically, when you create a task at run time.
Escalations are activated at a certain task state. The task will normally only be escalated because the expected task state has not been reached when the time limit for the escalation expires. However, it can also be triggered manually any time before the time limit expires by a user who has the appropriate authority. The time limit for the escalation is interpreted by the calendar that is specified for the task. You can specify multiple escalations (or escalations chains) that have the same activation state. An escalated task is put into the escalated substate.
- Ready
- For tasks in the ready state, you can define escalations for the
following situations:
- Escalate when the task is not claimed in time using the expected
task state of
claimed. - Escalate when the task is not completed in time using the expected
task state of
ended.
- Escalate when the task is not claimed in time using the expected
task state of
- Claimed
- To define an escalation for a to-do task or a collaboration task
that is in the claimed state when the task is not completed in time,
you must specify that the expected task state is
ended. - Running
- To define an escalation for an invocation task that is in the
running state when the invoked service does not return in time, you
must specify that the expected task state is
ended. If a task that is in the running state has an escalation defined for it, authorized users can trigger the escalation manually before the defined time limit expires. - Subtask started
- For to-do tasks or collaboration tasks, you can define an escalation that starts when the first subtask is started. This state can be used for tasks with single ownership, but is mostly used for tasks with parallel ownership. For these tasks, the expected end state must be ended.
When an escalation is raised, the people affected by the escalation (the escalation receivers) receive work items. Depending on the definition of the escalation, the escalation receivers might also receive an email notifying them that the task is escalated. The list of users to be notified is defined by a people query. This query must resolve to a set of individual user IDs.
You can define the escalation in the task model so that the priority of the task is automatically increased either for the first iteration only, or for every iteration of the escalation. In the administrative console, you can specify how you define priorities in your organization, by setting values for the Task.Priority.Highest and the Task.Priority.Lowest custom properties for Human Task Manager. For example, in your organization, you might use 0 to indicate the highest priority, other organizations might use 5 to express this priority.
Designing an escalation
- to whom the resulting work item should be assigned,
- the period of time before it should be escalated,
- the state that you want the task to be in when the escalation value times out (if it is not in this state, then an escalation is thrown),
- the action that should be taken in the case of an escalation,
- the mode of notification,
- whether the escalation should be performed again, and if so, how soon,
- whether the task priority should be increased during the escalation.
Lifecycle of an escalation
Here is a brief description of the stages that a typical escalation will go through.
- An instance of a task is created and, if it has an associated escalation, it remains inactive until the task reaches the activation state.
- When the task reaches the activation state, the first escalation of each chain is initialized with the starting of the Escalate timer, and the escalation moves to the waiting state.
- When a timeout occurs, the system checks to see if the expected task state has been reached. If the task has reached or passed it, the escalation state is changed to superfluous. If the expected state has not yet been reached, the escalation state is changed to escalated, and the escalation action is invoked, and one of the three possible actions occur (work item, email notification, or event handler notification).
- The escalation is repeated according to the Repeat notification every value.
- The escalation's priority is increased according to the Increase task priority value. The priority can be increased repeatedly if an auto-repeat duration is set.
Chained escalations
A chain of escalations is a series of escalations with the same activation state that are processed sequentially so that only one is active at any one time. The wait duration for each of the escalations in a chain is cumulative. That is, the timer on the second escalation in a chain will not start until the first escalation has timed out. This prevents escalations that are further along in the chain from timing out before the ones at the beginning. Also, keep in mind that an escalation with an expected state of end, cannot precede another escalation. Such a situation would never escalate, and you will receive a validation error if one exists in your diagram.
Parallel escalations
Parallel escalations are two or more escalations that are processed at the same time as opposed to sequentially. Each of the escalations has the same activation state but, in contrast to a chained escalation, its wait duration fires independently, and any one of them can have an end state as the expected state.
Escalations and task ownership
You have two choices of ownership pattern for your human tasks: single or parallel. One consequence of the choice of single or parallel ownership is in the handling of escalations. For single ownership you can define escalations that are triggered when the task is in the ready or claimed state. Such escalations are not applicable to a parallel ownership task. If you change the ownership of a task from single to parallel, you will be prompted for what to do with escalations that you have defined for the ready or claimed states. You can use them in a modified form, or you can delete them. See the related topic on Ownership Patterns for more details.