Versioning BPEL processes
Business processes evolve over time. They need to reflect changing environments and business needs. These changes might be business-driven changes, such as changes in regulations, or optimizations of processes. Business process applications can include long-running BPEL instances. These instances can run for weeks, months, or even years. This characteristic imposes specific requirements on the introduction of new versions of BPEL processes.
- In the likelihood that your BPEL process will need to be modified over time, but its callers will not. In such a case, you will want the existing callers to be able to seamlessly pickup the newest version of the process the moment it becomes effective.
- You have a solution where multiple versions of the same BPEL process must coexist. Although the solution as a whole cannot be uninstalled and reinstalled, you will need to be able to deploy new versions of the process in such a way as to ensure that new instances use the latest version and, wherever possible, existing instances also migrate to the latest version.
To create a new version of your BPEL process, create a new version of the corresponding module in Integration Designer, and make the changes that you need for the new process version. If the process is not part of a process application or toolkit, you must also give the new version of the process a valid-from date. To enable the migration of any existing process instances to the new version, you must also define a process migration specification in Integration Designer, and deploy it with the new version of the process.
After the new version of the BPEL process is deployed, new process instances can be created from the new version of the process. Existing instances continue to complete using the version that they were created and started with, or depending on the nature of the changes to the process, they can be migrated to the new version. In some situations, for example, when you want to correct an error in the process, you might also want to migrate the running instances of a process to the newer version so that they complete using this version.
Planning for different process versions
To create a version of a BPEL process, it is important that you plan ahead. Specifically, you will need to consider how the client interacts with the process, and how the process itself is set up. To allow for seamless introduction of new versions, it is a good idea to anticipate the need ahead of time, and set things up in the manner described in the associated topics.
One important consideration is whether instances of the process that are already running should move to the new version. If you want to migrate running instances you need to create a Migration Specification. If you are content to allow existing instances to use the old version you do not need to create a migration specification.
Differentiating process versions
A version is a copy of an existing process that is slightly different from the original. To understand how this differentiation takes place, you must first understand what identifies a version of a business process.
- same process component name
- same target namespace
- different valid-from date
- A process version that is part of the process application, or
part of a toolkit that is referenced by a process application can
be identified in one of the following ways:
- Process application acronym, process application snapshot name, and process name
- Process application snapshot ID and process name
- A process version that is part of a top-level toolkit (a top-level
toolkit is not referenced by a process application), or part of a
toolkit that is transitively referenced by the top-level toolkit can
be identified in one of the following ways:
- Top-level toolkit acronym, top-level toolkit snapshot name, and process name
- Top-level toolkit snapshot ID, and process name
- Correlation set specifications of different process versions need be the same.
- Interface specifications of different process versions need to remain the same. If you change the WSDL definition in any way, you need to change the BPEL process to incorporate those changes. If the WSDL has changed, you will need to load the new WSDL into IBM® Integration Designer, because when you deploy the module to the runtime environment, it requires the service definitions in the consumer and provider to match.
Of critical importance, the two versions must have the same name and namespace, but have different valid-from dates or snapshot ID's. In addition, where applicable, they must also have the same interface, and correlation set specifications. It is with different valid-from dates that multiple versions of the same BPEL processes are distinguished. In practice, at run time the process engine could use a new version of a process that is set to become valid today, even if an older version of that process was still being used.
Invoking versions of a BPEL process
When a client invokes a BPEL process, that client can be configured either to choose a specific version each time, or to pick up the currently valid version of the process. This is the basic concept behind early binding and late binding.
With early binding, a client is hard-wired to a process in such a way as to force a continued relationship between the two of them, even if another version of the process becomes available. In contrast, with late binding the relationship between the client and the process is dynamic in that it is resolved in the runtime environment.
If the caller instantiates a process using early binding, a specific version of the process is used to create that instance. If the caller uses a late binding, the currently valid version of the business process is used.
Process instance migration tools help you to update versions of running instances of processes in a late-binding situation. You create a process instance migration which, when deployed to the runtime environment, moves running instances of the process to the new version whenever possible. This facility is useful when you have very long-running processes.
- Using SCA wiring
- Using the Business Process Choreographer APIs (generic EJB API or generic web services API)
- Through the partner link extension in cases where a process that is acting as a client calls another BPEL process.
- Using the Business Process Choreographer APIs (generic EJB API or generic web services API)
Example
,
and click .