CWTKV0141E The duration attribute ''1'' defined on task model ''0'', contains a value ''2'' that is not valid. The calendar validation message is ''3''.

Explanation

If you specify a duration, the value must be valid for the calendar in use.

User response

Correct the duration value so that it is valid for the calendar that is used. In IBM Integration Designer, select the button in the top row of the canvas to open the task properties pages. On the Duration tab, choose the calendar type and enter a value in the duration field that conforms to the selected format. Press F1 to get more information about the format.