If you have attached the integration test client to a test configuration module and you later add another module to the test configuration, you will need to synchronize the Attach event with the test configuration to enable the integration test client to attach to the added test configuration module.

About this task

To synchronize an Attach event with a test configuration:

Procedure

  1. In the integration test client, click the Events tab to open the Events page.
  2. In the Events area, right-click the Attach event and select Synchronize Configuration. The Attach event and the test configuration are synchronized.