Monthly Schedule Settings (Select Time/Day or Time Interval/Day)

You can indicate the usual interval when the scheduled activity is run on certain days of every month.

To Complete these options: Example
Run the scheduled activity at one or more times on certain days of the month ___ (hours) ___ (AM or PM)

Select Day __

Click Add.

To run a business process or report at 10:15 a.m. on the first of every month, enter 10:15 a.m.,select day 1, and click Add.

You can add more than one specific time/day.

LDOM is the last day of the month.

Run the scheduled activity at certain intervals on certain days of the month Check here to select time interval.

From ____ To _____

Select Day __

Every ___ hours ___ minutes

Click Add.

To run a business process or report every 2.5 hours between noon and midnight on the first of every month:
  • Select Check here to select time interval.
  • Enter from 12:00 p.m to 12:00 a.m.
  • Enter day 1.
  • Enter every 2 hours 30 minutes.
  • Click Add.

You can add more than one time interval/day.

LDOM is the last day of the month.

Run the scheduled activity at startup At Startup Optional. Indicate whether to run the scheduled activity when Sterling B2B Integrator starts up. The scheduled activity also runs one time immediately after the schedule is saved in the database.