Step 12: Upgrade the Production environment
After you finish verifying the reports, push the upgraded application to Production.
- Go to TBM Studio.
- Select the Staging environment.
- On the Project ribbon, click Lock.
A brief pop-up message will indicate that the environment is locked. The environment is now ready to promote to Production.
- On the Projects ribbon, click Promotion Options,
then do one of the following:
- Click Promote Now. The upgrade is pushed to Production immediately.
- Click Promote Later to schedule when the upgrade will be published to
Production.
- On the Project ribbon, click Calculation Queue to verify the production build.
- Compare the build numbers for the Development, Staging, and Production environments.