You can update vault item values and manually sync changes to linked projects through the
Vault or Variables page.
Procedure
- Go to
to view the
list of existing vault items.
- Locate the vault item that you want to update and click the Update vault
item icon.
Modify the
Value field as needed.
Note: You
cannot update the Name and Item type
fields.
- Click Save.
- After a vault item is updated, the changes will not automatically reflect in the linked
projects. To update the linked projects, you can do either of the following steps:
- Update from the Vault page
Go to the Vault page
and click the Linked projects icon. In the list, projects with an Item
not in sync status indicate they need updating. Select the project you want to update and
click the Update selected option to synchronize it with the updated vault
item.
- Update from the Variable page
Go to the linked project’s
GeneralVariables
section, where you’ll see the existing variables and vault items. Click the drop-down arrow next to
the project name to reveal the associated vault item, then click the reload
icon to update the vault item’s value in the project.